Trade Finance BD
Menu
Search

· For authorised-dealer desks, exporters and importers

Bid, performance and advance payment bonds in Bangladesh

Key takeaways

  • Three bonds protect three stages of one contract: the tender (bid bond), delivery of the work (performance bond), and money paid up front (advance payment guarantee).
  • The name on the bond does not set its rules. Its text does: URDG 758, ISP98, or a bespoke form read under its governing law.
  • For a Bangladeshi applicant and a foreign beneficiary, paragraph 8 of FEPD-1 Circular No. 32 of 2 September 2026 lists what an AD may issue without asking Bangladesh Bank first.
  • An advance payment guarantee should shrink as the advance is earned. Under URDG 758 Article 13, tie each reduction to a named document or to something the guarantor can see in its own records.
  • A Bangladeshi importer paying in advance normally needs a repayment guarantee from a bank abroad (Circular 30, Part B ¶12).

What each bond does

All three are bank undertakings to pay the beneficiary on demand, up to a stated amount, if the demand meets the bond’s terms. They protect the beneficiary, usually a buyer or project owner, against the applicant, usually a supplier or contractor, failing to do something.

Two close relatives are the retention bond, which releases retention money early, and the warranty bond, which covers defects after handover. The drafting points below apply to them too.

How the bonds move through one contract

  1. Tender. The buyer’s tender documents state the bid bond amount, its form and its validity. The supplier’s bank issues the bid bond with the bid.
  2. Award. The winner signs the contract. Its bank issues the performance bond, and the buyer releases the bid bond. Losing bidders’ bid bonds are returned or simply expire.
  3. Advance. If the contract pays an advance, the bank issues the APG before the buyer remits. The APG usually equals the advance.
  4. Delivery. Each shipment or milestone earns part of the advance. The APG reduces by that amount. The performance bond stays in force until completion, or until a warranty bond replaces it.
  5. Close-out. The bonds end on their expiry date, by full reduction, or on a signed release from the beneficiary (URDG 758 Article 25(b)).
  6. If something goes wrong. The beneficiary presents a demand. How the guarantor examines and pays it is covered in our URDG 758 demand guide.

Bangladesh rules

Bangladeshi exporters and suppliers bidding abroad

FEPD-1 Circular No. 32 is the consolidated circular on loans, overdrafts, guarantees and external borrowing. Paragraph 1 asks ADs to observe the ICC rules for guarantees, credits and standbys. Paragraph 8 sets out guarantees on behalf of residents in favour of non-residents:

When an exporter receives an advance, FEPD-1 Circular No. 26, Part A ¶22, also applies. The exporter files an Advance Receipt Voucher. The advance must not bear interest. The export must normally happen within one year. That one-year limit does not apply when the advance is received against a performance bond, bank guarantee or standby LC.

Bonds for projects and tenders inside Bangladesh

Importers paying in advance

FEPD-1 Circular No. 30, Part B ¶12(b), lets an AD remit an import advance if the supplier provides a repayment guarantee from a bank abroad that is acceptable to the AD. It waives the guarantee for advances up to USD 20,000, subject to five conditions. Part H ¶3(a) restates this and allows up to USD 50,000 without a guarantee when paid from an exporter’s retention quota (ERQ) account. Larger advances without a guarantee go to Bangladesh Bank case by case.

Parties and documents

Party or documentWhat to check
Applicant (supplier or contractor)Credit limit, counter-indemnity, collateral, export record
Beneficiary (buyer or project owner)Bona fides, sanctions screening, tender authority
Guarantor (issuing bank)Which Circular 32 paragraph authorises the issue
Counter-guarantorNeeded when a local bank in the beneficiary’s country issues the bond; the chain must match
Tender documents or contractRequired bond wording, amount, currency, validity
Bond textRules incorporated, expiry, reduction clause, demand documents, governing law
Reduction evidenceShipping documents, acceptance certificates, or the bank’s own payment records
Release letterSigned release from the beneficiary ends a URDG bond even if the original is not returned

Risks and common mistakes

Illustrative example

All names and figures are hypothetical and chosen only to show the arithmetic. PQR Engineering Ltd in Chattogram wins a USD 800,000 tender to supply switchgear to a buyer abroad, delivered in four equal shipments. XYZ Bank PLC is its AD.

StageBondAmount
TenderBid bond, ¶8(1)(b)USD 16,000, released on award
ContractPerformance bond, ¶8(3)(a)USD 80,000 until final acceptance
Advance receivedAPG, ¶8(3)(c)USD 160,000 at issue
After shipment 1 (USD 200,000)APG reduces by 20% of shipment valueUSD 120,000
After shipment 2APGUSD 80,000
After shipment 3APGUSD 40,000
After shipment 4APGNil; bond terminates

The APG reduction clause names the trigger: “a copy of the bill of lading for each shipment presented to the guarantor”. Because the advance was received against a bank guarantee, the one-year export limit in Circular 26 ¶22(d) does not apply. The advance still needs an ARV and must carry no interest.

How the bonds compare

Bid bondPerformance bondAdvance payment guaranteeStandby LC
Protects againstBidder withdrawing or refusing the awardNon-performance of the contractLoss of an unearned advanceAny agreed default, often payment
Usual lifeBid validity periodUntil completion or warrantyUntil the advance is earnedAs drafted
Reduces over time?NoSometimes, at milestonesYes, shouldAs drafted
Rules, if incorporatedURDG 758 or a local formURDG 758 or a local formURDG 758 or a local formISP98 or UCP 600
Circular 32 hook, resident applicant¶8(1)¶8(1)(a), ¶8(3)¶8(3)(c)¶8 and ¶13, by purpose

For the difference between a performance guarantee and a standby LC, see performance guarantee vs standby LC.

Frequently asked questions

Does an AD need Bangladesh Bank approval to issue a performance bond for an exporter?

Not if the case fits FEPD-1 Circular No. 32 ¶8(3)(a) or ¶8(3)(c) and the bank’s normal credit norms. Cases outside the listed paragraphs need prior approval.

Can the buyer call the bond even if we delivered on time?

A demand guarantee is independent of the contract (URDG 758 Article 5). If the demand complies, the bank pays. The applicant’s dispute about performance is then with the beneficiary under the contract, or in court in exceptional cases under the governing law.

Must the original bond be returned before it ends?

Not under URDG 758. Article 25(b) ends the guarantee on expiry, when nothing remains payable, or on a signed release, whether or not the document is returned. A bond that does not incorporate URDG must be read on its own words and governing law.

My supplier wants an advance. What must I get?

Above USD 20,000, a repayment guarantee from a bank abroad that your AD accepts (Circular 30 Part B ¶12(b)). Below that, the waiver conditions in ¶12(b)(i)–(v) must be met.

Sources

Bangladesh Bank, FEPD-1 Circular No. 32, 2 September 2026 (loans, overdrafts, guarantees and external borrowing): ¶1, ¶8(1)–(3), ¶11, ¶12, ¶13. Open the cited source.

Bangladesh Bank, FEPD-1 Circular No. 26, 30 July 2026 (export): Part A ¶22. Open the cited source.

Bangladesh Bank, FEPD-1 Circular No. 30, 13 August 2026 (import): Part B ¶12; Part H ¶3(a). Open the cited source.

ICC Uniform Rules for Demand Guarantees, 2010 revision, ICC Publication No. 758: Articles 5, 7, 11, 13, 15 and 25. Open the cited source.